Shanxi Yongji Thermal Power Plant, 2 × 350 MW
The 2×350 MW large‑capacity, small‑capacity cogeneration desulfurization and denitrification project at the Yongji Thermal Power Plant in Shanxi Province is located in Yongji City, Yuncheng Prefecture, Shanxi Province. Project scale: two 350 MW ultra‑supercritical thermal power generating units, with desulfurization and denitrification facilities constructed concurrently. Total investment: RMB 100 million. 1. Procedures: All preliminary procedures have been completed. 2. Design: The design phase is underway, undertaken by the Shanxi Provincial Electric Power Survey and Design Institute. 3. Civil construction: Civil construction has not yet commenced; the supervision tender is currently being conducted, with a deadline of July 5, 2013. 4. Equipment procurement: The tender for the main equipment has been concluded.