21

2022

08

Key Points for the Construction and Installation of Electric Control Valves


1. Electric control valve The installation location, height, and inlet/outlet orientation must comply with the design requirements, and the connections shall be secure and tight.
2. Electric control valves can be connected to pipelines via various top‑mounting configurations. The primary connection methods are threaded joints; for temperatures exceeding 350°C, flanged or welded connections are recommended. Since bolts, flanges, and gaskets may experience creep and relaxation at elevated temperatures, high‑temperature‑resistant bolt materials should be selected.
3. Prior to installation, the electric control valve must be inspected, and its nameplate shall comply with the provisions of the current national standard GB 12220, “General Valve Marking.” For valves installed on main pipelines that are subject to isolation, strength and tightness tests shall be conducted; only those that pass may be put into service. Other valves need not undergo separate testing and shall instead be tested during the system pressure test.
4. During the strength test of an electric control valve, the test pressure shall be 1.0 times the nominal pressure, and the duration shall be no less than 5 minutes; the valve body and packing shall exhibit no leakage. For the tightness test, the test pressure shall be 1.1 times the nominal pressure; the test pressure must remain constant throughout the test period, which shall comply with the specified duration, and the valve disc face shall show no leakage. Nominal diameter: DN15–500.